Project Profile Contractor Owner Partners Engineer Completion Date Project Value
Maroon Creek Bridge Replacement BTE/Atkinson/Littleton Electric Colorado DOT Holy Cross, Aspen, Qwest, CDOT, Comcast,
Aspen IT
Parsons 2008 14 Million
 
Maroon Creek Bridge Replacement
click image to enlarge
Project Summary
  • Through a VE proposal, United Fiberglass convinced Parsons and CDOT to approve an 8-way and 12-way fiberglass duct bank in lieu of heavier PVC and Galvanized Rigid Steel on the new Maroon Creek Bridge
  • Our proposal resulted in a 50% material and labor reduction
  • System will consist of 10,800’ of fiberglass conduit and associated hangers and accessories